Nvidia Chip Shortages Deepen as Goldman Sachs Forecasts 52 GW Data Centre Expansion and OpenAI Faces IPO Challenges
Nvidia is facing longer delivery times across its artificial intelligence chip portfolio as demand for computing infrastructure continues to strain supplies. The shortages come despite a sharp correction in technology stocks and growing investor concerns over the profitability of AI infrastructure investments.
Taiwan-based original design manufacturers have reported significantly longer waiting periods for Nvidia’s B300 and GB300 products, according to Commercial Times.
Delivery lead times for B300 graphics processing units (GPUs) have increased to between 26 and 40 weeks, while GB300 systems face waiting periods of approximately 14 to 26 weeks.
Most new orders placed over the next two quarters are unlikely to be delivered before the second or third quarter of 2027.
Workstation-class superchips also face delivery times of approximately 26 weeks, placing further pressure on consumer GPU availability.
Nvidia is reportedly preparing to reduce shipments of its GeForce RTX 50 series. Mass production of the RTX 60 series, originally targeted for late 2027, could also be delayed.
Nvidia Chip Delivery Lead Times
Reported waiting periods for new orders
| Product | Delivery period | Supply outlook |
|---|---|---|
| B300 GPUs | 26–40 weeks | Extended waiting periods |
| GB300 systems | 14–26 weeks | Supply constraints |
| Workstation superchips | Approximately 26 weeks | Limited availability |
| GeForce RTX 50 series | Not specified | Possible shipment reductions |
| GeForce RTX 60 series | Original production target: late 2027 | Potential production delay |
Source: Commercial Times. Lead times and potential production changes are based on industry reports.
US President Donald Trump told the New York Post that he would pardon Nvidia CEO Jensen Huang if necessary, although he did not expect Huang to require one. Trump said Huang should tell the truth during his upcoming congressional testimony and need not invoke the Fifth Amendment.
Trump also revealed that he had considered the US government acquiring an equity stake in Nvidia, although no formal proposal had been made.
US Trade Representative Jamieson Greer described Nvidia as structurally important and emphasised the need to maintain its leadership. He also said the administration was closing certain loopholes in chip export controls while seeking to balance economic and national security interests.
Goldman Sachs Forecasts 52 GW of Additional Data Centre Capacity
Goldman Sachs expects the expansion of US data centre power capacity to continue through 2028, despite rising concerns over technology valuations and infrastructure financing.
The bank projects 52 gigawatts (GW) of additional capacity by 2028 as companies construct larger data centres with higher electricity requirements.
US data centre power capacity and electricity demand have increased nearly 30% in 2026. Data centres have accounted for more than one-third of the growth in total US electricity demand.
US Data Centre Power Expansion
Goldman Sachs infrastructure and electricity demand outlook
Source: Goldman Sachs. The 52 GW figure represents projected additional capacity rather than total installed capacity.
Rapid infrastructure expansion could worsen existing electricity supply constraints and increase demand for natural gas used in power generation.
However, Goldman Sachs warned that policy changes following the US midterm elections could moderate growth. A divided government and tighter scrutiny of data centre construction could restrict future capacity additions.
JPMorgan also believes underlying demand for AI computing capacity remains stronger than current market sentiment suggests. Its strategists argue that temporary supply bottlenecks and valuation corrections do not necessarily indicate a slowdown in AI adoption.
The bank sees potential upside of 20% to 25% in Asian AI-related stocks if anticipated earnings downgrades do not materialise. Server manufacturers, semiconductor testing companies, substrate suppliers and optical component makers were identified as potential beneficiaries.
Anthropic’s Post-IPO Decline Raises Questions Over OpenAI’s Funding Plans
Growing demand for computing infrastructure contrasts with weakening investor confidence in the financial returns generated by AI companies.
Anthropic’s reported decline below its $83 initial public offering (IPO) price has raised questions about investor appetite for major AI company listings.
According to Daniel Dolnik, head of US single-stock options trading at Optiver, Anthropic’s options trading volume on Tuesday reached just 25% of SpaceX’s volume on its second day of options trading.
Although a significant proportion of Anthropic options activity continued to favour further share price gains, retail investor enthusiasm appeared to have weakened.
The Wall Street Journal reported that Anthropic’s post-listing decline had complicated OpenAI’s potential 2027 IPO plans. OpenAI is seeking to improve financial performance while dealing with senior executive departures and increasing competition.
OpenAI reportedly generated $10 billion in third-quarter revenue, compared with Anthropic’s $17 billion, while recording larger operating losses.
Reported Q3 Revenue: Anthropic vs OpenAI
Revenue in billions of US dollars
Source: The Wall Street Journal. Revenue figures and investment plans are reported estimates and should not be treated as audited financial disclosures.
OpenAI reportedly plans to invest approximately $750 billion in computing infrastructure by 2030, making a public listing an important potential source of financing.
The company aims to improve the competitiveness of its AI models and expand its enterprise market share before pursuing a listing.
However, delaying an IPO could expose OpenAI to weaker investor demand if enthusiasm for AI investments continues to decline.
Persistent chip shortages and rising electricity demand indicate continued infrastructure expansion, while weakening technology valuations highlight concerns about financing costs, operating losses and future profitability.
What It Means
AI infrastructure demand and the financial performance of AI companies are producing different signals.
Chip suppliers continue to face extended order waiting periods, suggesting that computing hardware remains in high demand. Electricity suppliers and natural gas producers could also benefit from additional data centre construction.
However, companies developing AI models face substantial infrastructure expenses. Their ability to generate revenue and eventually profits will determine whether these investments deliver sustainable financial returns.
For consumer GPU buyers, competition for manufacturing capacity could result in reduced product availability or delayed hardware releases.
The outlook depends on whether companies can maintain access to financing, expand computing capacity and increase revenue sufficiently to justify their spending commitments.
What to Watch
- Nvidia B300 and GB300 delivery schedules through 2027.
- Potential RTX 50 series shipment reductions and RTX 60 production delays.
- US chip export control changes and Jensen Huang’s congressional testimony.
- Data centre construction approvals, electricity supply constraints and natural gas demand.
- OpenAI’s financial performance, infrastructure financing requirements and potential IPO timeline.
Market Impact
- Nvidia B300 delivery times: 26 to 40 weeks. Extended waiting periods reflect continuing AI hardware supply constraints.
- US data centre expansion: 52 GW forecast by 2028. Additional infrastructure could support electricity and natural gas demand.
- US data centre electricity demand growth: Nearly 30% in 2026. Rapid expansion could increase pressure on electricity supply.
- Asian AI stocks: Potential 20% to 25% upside projected by JPMorgan. The outlook depends on anticipated earnings downgrades not materialising.
- OpenAI infrastructure investment plans: Approximately $750 billion through 2030. Financing requirements remain substantial.
- Anthropic reported IPO price: $83. Trading below the offering price raises concerns over investor demand for AI company listings.
Why is Nvidia facing AI chip shortages?
Taiwan-based manufacturers have reported extended delivery lead times across Nvidia’s AI computing products. B300 GPUs face waiting periods of 26 to 40 weeks, while GB300 systems face delays of 14 to 26 weeks. Persistent supply constraints are also reportedly affecting workstation and consumer graphics products.
Could Nvidia’s RTX 60 series launch be delayed?
Nvidia’s RTX 60 series mass production, originally targeted for late 2027, could reportedly be delayed as AI and workstation chip supply constraints affect consumer GPU availability. The company is also reportedly preparing to reduce GeForce RTX 50 series shipments. A revised production schedule has not been confirmed.
What is Goldman Sachs’ forecast for US data centre power capacity?
Goldman Sachs expects US data centres to add 52 GW of power capacity by 2028. Data centre power capacity and electricity demand have already increased nearly 30% in 2026. The bank expects continued infrastructure expansion to support electricity consumption and natural gas demand, although regulatory risks remain.
How could Anthropic’s stock performance affect OpenAI’s IPO?
Anthropic’s reported post-IPO decline has raised concerns about investor appetite for major AI company listings. According to The Wall Street Journal, OpenAI is seeking to improve its financial performance and competitiveness before listing. Weakening investor enthusiasm could complicate the timing and financing prospects of its potential IPO.
How much does OpenAI reportedly plan to invest in AI infrastructure?
OpenAI reportedly intends to invest approximately $750 billion in computing infrastructure by 2030. The scale of these investment plans makes access to capital important. A potential IPO could provide an additional financing avenue, although operating losses, competition and weaker investor sentiment may complicate its plans.